The field implementation of the Long Form SP2020 pre-update activities starts on schedule, 17 – 31 October 2021. This activity involves 120 officers, consisting of PCL, PML and Koseka who will serve in 309 Census Blocks.
AIM
The objectives of the pre-update activities are as follows:
Updating/updating family or household lists based on SP2020 results using the CAPI application.
Updating/updating building points on CAPI applications.
As an illustration of cases found in the field so that more mature planning can be carried out for SP2020 long form activities next year.
Business Process Pre-Update Long Form SP2020
• Need to update prelist for LF SP2020
Prelist available based on SP2020 (condition is almost 1 year)
• Planning for CAWI and CATI LF SP2020 modes
LF SP2020 FY 2022 will use multimodal including CATI and CAWI which requires a family/household phone number and email
• Improvement of field cases (BS with certain criteria)
BS formed from one whole SLS and SLS fractions
BS formed from one SLS fraction
BS formed from several SLS shards
CB affected (remaining CB formed type a, b, and c)
SCOPE
Pre-update samples were 151 056 Census Blocks. Pre-update sample BS taken from LF sample (268,431 BS). No Pre-Upgrade BS sample replacement
IMPLEMENTATION SCHEDULE
No. Description of Activities Schedule
(1) (2) (3)
1 Pre-update field implementation 17-31 October 2021
2 Pre-update monitoring and supervision 17-31 October 2021
List of instruments used (CAPI Region):
e-Form or assignment LF.SP2020-DSBS PP
e-Form or assignment LF.SP2020-PP
WB-2020 map with building points on selected census blocks (printed) BS 2020 digital map with building points
WA maps for villages/kelurahan in selected census blocks (without building points)